A project manager is trying to ensure the quality of the design and reduce the number of potential defects. The project manager would like to use the fishbone diagram to perform this analysis. This type of modeling relies on:
A. Prioritizing the specific event.
B. Variance in the process over time.
C. Causes of a specific event.
D. Determining the number of events.
During which of the following phases should project requirements be determined?
A. The initiating phase
B. The execution phase
C. The planning phase
D. The monitoring phase
The project manager has received an approved change request. Which of the following actions should the project manager take NEXT?
A. Schedule a meeting with the change advisory board to discuss the impact of the change
B. Perform a probability and impact assessment on the approved change
C. Hold a team meeting to ensure the change is immediately implemented
D. Develop a plan to incorporate the change into the project