Which of the following MUST be clearly defined in a project charter?
A. Quality
B. Scope
C. Action items
D. WBS
The project manager is reviewing the Pareto chart to identify if the life cycle of a deliverable is producing software bugs. Which of the following are represented in the chart? (Select TWO).
A. Number of work units affected by the bug
B. Percentage of bug types occurring
C. Software bug counts
D. Root cause of bug occurrence
E. Affect of the bug occurrence
A project team has determined it will need to source data from a system that was not part of the project scope. The role of the project manager is to analyze which of the following impacts?
A. Technical design, schedule, and budget
B. Business process impacts and resourcing
C. New software and hardware requirements
D. Schedule, budget, and quality
Which of the following is the FIRST step in a proper change management procedure?
A. Coordinate with appropriate stakeholders
B. Update the project plan
C. Perform impact analysis
D. Identify a change
While working on a project, an unforeseen event arises that impacts a project objective. Which of the following should be updated as a result?
A. Stakeholder register
B. Issue log
C. Risk register
D. Change log
Which of the following should be included in a business case? (Select TWO).
A. A budget estimate with a plus to minus 10%
B. Benefits to the company
C. Project Milestones
D. Cost Benefit Analysis
E. One proposed option to address the issue
In a functional structured organization, which of the following is a common cause of conflict with project team members?
A. Inadequate budget
B. Failure to communicate project goals and objectives
C. Competing demands for resources
D. Lack of proper training
As a way to systematically identify risks inherent to a project, which of the following tools would be used?
A. Risk response plan
B. Risk probability and impact matrix
C. Risk Matrix
D. Risk Breakdown Structure
During customer acceptance, a project manager meets with the stakeholders who claim a bridge was built with two toll gates instead of three. Which of the following documents would clarify the discrepancy?
A. Scope Statement
B. Lessons Learned
C. Closeout report
D. Risk Management Plan
A project scope document should include which of the following items? (Select TWO).
A. Cost control
B. Continuous service improvements
C. Key performance indicators
D. Detailed objectives
E. Risk management plan