The project manager crashes a project that is behind schedule and under-budget. Which of the following will be the intended result?
A. The project will be behind schedule and over-budget.
B. The project will be on schedule but over-budget.
C. The project will be on schedule and on-budget.
D. The project will be behind schedule and on-budget.
Which of the following BEST describes the definition of a project?
A. Work undertaken to deliver a unique product or service
B. Major work initiatives requested by an Executive Sponsor
C. A yearly list of strategic goals for a company
D. Work that can be decomposed to the task level
A project manager is working with a large team on an important project. Many of the team members work remotely. The project manager requires each team member to submit weekly status reports at a certain time each week. One team member consistently submits late status reports. Which of the following should the project manager consider FIRST?
A. Time zones for various work locations
B. Necessity of weekly status reports
C. Format of the status report
D. Past performance reviews of the team member