Which of the following are process groups in the project life cycle? (Select Three).
A. Accepting
B. Mitigating
C. Avoiding
D. Initiating
E. Closing
F. Planning
A project team member is uncertain how many activities are required to complete a task. Which of the following documents should be referenced?
A. Key Performance Indicators (KPIs)
B. Project charter
C. Work Breakdown Structure (WBS)
D. Statement of Work (SOW)
Which of the following should be created in the project closing documentation? (Select Two).
A. Closure report summarizing costs
B. Responsibility assessment matrix
C. Lessons learned
D. Project timeline
E. Statement of Work (SOW)
Project team members are confused about their roles on a project. Which of the following is the FIRST technique the project manager can use to define their roles?
A. Create a resource assignment matrix.
B. Ask team members to define their roles.
C. Have project sponsor assign their roles.
D. Conduct stakeholder meeting to determine expectations.
Which of the following estimating types requires the MOST effort when creating a work breakdown structure (WBS)?
A. Expert judgment
B. Top-down
C. Bottom-up
D. Rough order of magnitude
A project manager added some experienced team members to work on certain project activities in conjunction with inexperienced team members because the project is behind schedule. Which of the following BEST describes the technique the project manager is using?
A. Schedule optimization
B. Fast tracking
C. Resource management
D. Crashing
Which of the following is the MOST common relationship used, when constructing a project schedule network diagram?
A. Start-to-Finish
B. Finish-to-Start
C. Start-to-Start
D. Finish-to-Finish
Which of the following would be the BEST tool to estimate activity time durations?
A. Gantt chart
B. CPM
C. Estimating model
D. PERT
If the EV is $3,000 and the AC is $4,000, which of the following would be the CPI for the project?
A. .50
B. .75
C. 1.25
D. 1.75
Which of the following documents should be used to present the length of identified tasks?
A. CPM
B. Key event/activity list
C. PERT
D. Gantt