What metric CANNOT be deleted from Critcal to Quality (CTQ)?
A. Goal
B. Controlled
C. Measured
D. Predicted
In the dashboard Image below, what is the red square indicatng?
A. The task is Complete
B. The task is not complete but not late or at risk
C. The task is a Milestone and is pending
D. The task is late
Which dependency code do you assign if the current task CANNOT fnish untl another task starts?
A. Finish-To-Finish
B. Finish-To-Start
C. Start-To-Finish
D. Start-To-Start