What is a critcal path for a project?
A. It is the sequence of tasks, beginning to end, that takes the longest
B. It is the sequence of tasks that has the most milestones
C. It is the path that has the most phase gates
D. It is the path that takes the shortest sequence tme
The default tme line increment for a Gant Chart is:
A. day
B. week
C. 12 hours
D. hour
Afer an Issue has been assigned to a user and promoted to the Assign state:
A. an email/IconMail notfcaton is sent to the user
B. a Task is created and sent to the user's task list
C. a route is created
D. the WBS is suspended
When searching for a Program, how many Programs can be displayed per page?
A. Unlimited
B. 100
C. Confgurable
D. 1000
When creatng a Route, if Approve is selected in the Acton feld, the task assignee must:
A. choose an approval status only
B. enter a comment only
C. mark the task complete only
D. enter a comment and choose an approval status
What happens when a task is completed by a user?
A. Promotes the task to Finish
B. Completes the route
C. Enters the due date in the Completon date feld
D. The next order number task is started
When viewing a dashboard and the slip date is 0 to 4 days later than the estmated end date, the slip date will be:
A. Red
B. Green
C. Yellow
D. Black
If you want to allow a person to add fles to a route, which access rights to you need to give to this person?
A. Add
B. Read Write
C. Any of these will do it
D. Add Remove
What does the red square in the following image, indicate?
A. The task is not complete and the current date is afer the task estmated fnish date
B. The task is not complete and there are less than 5 days before the project's estmated fnish date
C. The task is complete
D. The task has not started
A Work Breakdown Structure is a hierarchy of ...?
A. Tasks
B. Roles
C. Deliverables
D. Routes