Which is a purpose of the 'initiating a project' process?
A. To produce a stage plan for each stage of a multi-stage project
B. To enable the project board to decide whether it is worthwhile to initiate a project
C. To provide a fixed point at which acceptance for the project product is confirmed
D. To enable an organization to understand the work needed to deliver the project's products
What is documented in the project plan to support the 'manage by exception' principle?
A. The project's tolerances for cost and time
B. A project product's quality criteria
C. The expected project benefits
D. Activities to mitigate project risks
Which product summarizes progress and is used to decide whether to amend the project scope or stop the project?
A. Checkpoint Report
B. End Stage Report
C. End Project Report
D. Product Status Account
Which is a purpose of a Product Description?
A. Provide the cost tolerance available for individual products
B. Define reporting frequency
C. Record the quality checks completed for the End Stage Report
D. Document the level of quality required of a product
How many tasks does the product-based planning technique describe?
A. One
B. Two
C. Three
D. Four
Which characteristic of a project reflects that there are different perspectives and motivations for customers and suppliers?
A. Change
B. Cross-functional
C. Unique
D. Risk
Which is NOT included in the PRINCE2 definition of a project?
A. A project is a temporary organization
B. A project'spurpose is to deliver one or more business products
C. A project is part of business as usual'
D. A project is based on an agreed Business Case
Which project characteristic suggests that projects should have a defined start and a defined end?
A. Change
B. Temporary
C. Cross-functional
D. Risk
Which is the base product against which the Project Board can assess progress, issues and ongoing viability questions?
A. Project Brief
B. Project Initiation Documentation
C. Project mandate
D. Benefits Review Plan
Which of the following is FALSE regarding an Exception Report?
A. It describes a forecast deviation of stage or project level tolerance
B. It contains recovery options and a recommendation
C. It replaces a Stage Plan or Project Plan
D. It describes the consequences of the deviation