Which TWO are the purposes of a highlight report?
1.
To describe the MoSCoW priority of user stories.
2.
To summarize the status of a work package.
3.
To summarize the stage status.
4.
To report any potential issues and risks
A. 1 and 2
B. 2 and 3
C. 3 and 4
D. 1 and 4
In which area is Agile strongest when blending with PRINCE2?
A. Product delivery
B. Project management
C. Project direction
D. Product management
Which is NOT one of the core concepts of Lean Startup that apply to PRINCE2?
A. To use empiricism, based on knowledge that comes from experience
B. To build, measure, learn from your experiences
C. To create a minimum viable product to manage uncertainty
D. To fail fast, if you are going to fail
In Scrum, what answers the question `what can be done this sprint?'
A. Daily scrum
B. Sprint review
C. Sprint planning
D. Increment
During which process should release planning be done for the FIRST time?
A. Initiating a project
B. Managing a stage boundary
C. Managing product delivery
D. Controlling a stage
Which statement explains how the `learn from experience' principle is applied in an agile context?
A. It focuses on the prioritization and decomposition of requirements
B. It integrates releases within management stages
C. It is supported by the `inspect and adapt' concept
D. It provides guidance on mapping PRINCE2 roles to an agile environment
When tracking progress, which term describes using agile techniques at the delivery level, and traditional techniques at the direction and management levels?
A. Preferable
B. Typical
C. Effective
Which two statements are key responsibilities of supplier representative?
1.
They highlight areas that the project may impact from a technical perspective.
2.
They are partially assigned to the delivery team.
3.
They create the project's specialist products.
4.
They prioritize requirements.
A. 1 and 2
B. 2 and 3
C. 3 and 4
D. 1 and 4
Which is a purpose of the quality theme?
A. To define the specific conditions that enable a product to be usable
B. To determine how the means of delivering products is communicated
C. To evaluate whether the project continues to be achievable
D. To assess any potential improvements to a product
How does agile address the risk associated with the project not being fully understood at the beginning?
A. By allowing a lot of detail at the start
B. By avoiding too much detail at the start
C. By requiring details at the start
D. By preventing the analysis of details at the start