Which is a purpose of the Controlling a Stage process?
A. Produce a Team Plan for the work to be assigned to a Team Manager
B. Select and implement actions that will resolve deviations from a plan within tolerance
C. Obtain approvals for products delivered in a Work Package
D. Update a Project Plan to incorporate the actuals from a Stage Plan
Identify the missing word in the following sentence. A member of the Project Board is responsible for [ ? ] assurance.
A. quality
B. supplier
C. risk
D. product
Which should be funded by a change budget?
A. Increase in agreed scope
B. Increase in agreed scope
C. Increase in agreed scope
D. Handover activities
What product defines the reporting requirements between the Project Manager and Team Manager?
A. Project Brief
B. Product Description
C. Team Plan
D. Work Package
Which does a Project Manager produce to define and control the work to be done?
A. Configuration Item Record
B. Stage scope tolerance
C. Team Plan
D. Work Package
Which statement is true for ALL project stakeholders?
A. Internal to the corporate organization
B. May either affect or be affected by the project
C. Review the Communication Management Strategy
D. Support the project
What is the collective name for individuals or groups who may be affected by a project?
A. Customers
B. Project Support
C. Stakeholders
D. Team members
Which is part of quality control?
A. Undertake quality reviews
B. Write Product Descriptions
C. Provide assurance that the project is being conducted properly
D. Document the customer's quality expectations
Identify the missing words in the following sentence. The role of [ ? ] is responsible for carrying out a risk response action to respond to a particular risk.
A. Project Assurance
B. Project Support
C. the risk actionee
D. the risk owner
Which is a purpose of an End Project Report?
A. Identify individuals or groups that need to be told that the project is coming to an end
B. Review how well the project performed against the Project Initiation Documentation used to authorize it
C. Identify individuals or groups that are responsible for measuring the expected benefits after the project has closed
D. Ensure that key project information is archived and made secure