Want to pass your PMI Scheduling Professional PMI-SP exam in the very first attempt? Try Pass2lead! It is equally effective for both starters and IT professionals.
VCE
Holly is the project manager of her project. She has chosen to crash the project due to time constraints that have been imposed on her project. When Holly crashes the project what project document must be updated to reflect this change to the approach?
A. Develop schedule process
B. Risk register
C. Project risk management plan
D. Activity attributes
Examine the figure given below.
In this project network diagram, what is the total float for Activity I?
A. Three
B. Zero
C. Five
D. One
You are the project manager of the NQQ project. You are working with your project team to create the activity duration estimates for the project. For each reported activity duration, your project team offers you an addition of five percent extra time for risks, errors, or aggressive estimating. What does Parkinson's Law state about this scenario?
A. Work expands to fulfill the amount of time allotted to it.
B. Risks will be allowed into activities in which management creates risk provisions.
C. Laborers will create errors when time has been allotted for errors to exist.
D. Errors will be allowed into assignments when management creates error opportunity.