Complete the sentence. Actions arising from the Business Transformation Readiness Assessment technique should be incorporated in the
A. Architecture Requirements Specification
B. Architecture Roadmap
C. Implementation Governance Model
D. Implementation and Migration Plan
Consider the following statement.
Projects may cycle between ADM phases, in planned cycles covering multiple phases.
What does it illustrate?
A. Requirements management
B. Iteration
C. Implementation governance
D. Enterprise Architecture
What is an objective of the ADM Preliminary Phase?
A. To develop a vision of the business value to be delivered by the proposed enterprise architecture
B. To select and implement tools to support the Architecture Capability
C. To obtain approval for the Statement of Architecture Work
D. To create the initial version of the Architecture Roadmap
What is an objective of the ADM Implementation Governance Phase?
A. To provide continual monitoring of the governance framework
B. To ensure conformance for the target architecture
C. To finalize the Implementation and Migration Plan
D. To establish the resources for architecture governance
Exhibit
Consider the illustration showing an architecture development cycle Which description matches the phase of the ADM labeled as item 2?
A. Conducts implementation planning for the architecture defined in previous phases
B. Establishes procedures for managing change to the new architecture
C. Operates the process of managing architecture requirements
D. Provides architectural oversight for the implementation
Which ADM phase focuses on defining the problem to be solved, identifying the stakeholders, their concerns, and requirements?
A. Phase
B. Preliminary Phase
C. Phase
D. Phase A
Which of the following does the TOGAF standard describe as a package of functionality defined to meet business needs across an organization?
A. An application
B. A solution architecture
C. A building block
D. A deliverable
Complete the sentence. When considering agile development, Architecture to Support Portfolio will identify what products the Enterprise needs, the boundary of the products, and what constraints a product owner has; this defines the Enterprise's
A. risk tolerance
B. business continuity
C. backlog
D. operating model
Please read this scenario prior to answering the question
Your role is that of a consultant to the Lead Enterprise Architect to an international supplier of engineering services and automated manufacturing systems. It has three manufacturing plants where it assembles both standard and customized products for industrial production automation. Each of these plants has been operating its own planning and production scheduling systems, as well as applications and control systems that drive the automated production line.
The Enterprise Architecture department has been operating for several years and has mature, well-developed architecture governance and development processes that are based on the TOGAF Standard. The CIO sponsors the Enterprise Architecture.
During a recent management meeting, a senior Vice-President highlighted an interview where a competitor company's CIO is reported as saying that their production efficiency had been improved by replacing multiple planning and scheduling systems with a common Enterprise.
Resource Planning (ERP) system located in a central data center. Some discussion followed, with the CIO responding that the situations are not comparable, and the current architecture is already optimized.
In response, the Architecture Board approved a Request for Architecture Work covering the investigations to determine if such an architecture transformation would lead to improvements in efficiency. You have been assigned to support the architecture team working on this project.
A well-known concern of the plant managers is about the security and reliability of driving their planning and production scheduling from a remote centralized system. Any chosen system would also need to support the current supply chain network consisting of local partners at each of the plants.
Refer to the scenario
You have been asked to explain how you will initiate the architecture project.
Based on the TOGAF Standard, which of the following is the best answer?
A. You would research vendor literature and conduct a series of briefings with vendors that are on the current approved supplier list. Based on the findings from the research, you would define a preliminary Architecture Vision including summary views, high-level requirements, and high-level definitions of the baseline and target environments from a business, information systems, and technology perspective. You would then use that to build consensus among the key stakeholders.
B. You would conduct a pilot project that will enable vendors to demonstrate potential off-the-shelf solutions that address the concerns of the stakeholders. Running a pilot project will save time and money later in the process. Based on the findings of that pilot project, a complete set of requirements can then be developed that will drive the evolution of the architecture. Once the requirements are completed, a formal stakeholder review should be held, and permission sought to proceed to develop the target architecture.
C. You would hold a series of interviews at each of the manufacturing plants using the business scenarios technique. This will allow you to understand the systems and integrations with local partners. You would use stakeholder analysis to identify key players in the engagement, and to understand their concerns. You will then identify and document the key high-level stakeholder requirements for the architecture. You will then generate high level definitions of the baseline and target architectures.
D. You would develop baseline and target Architectures for each of the manufacturing plants, ensuring that the views corresponding to selected viewpoints address key concerns of the stakeholders. A business case, together with performance metrics and measures should be defined to ensure the architecture meets the business needs. A consolidated gap analysis between the architectures will then validate the approach and determine the capability increments needed to achieve the target state.
Please read this scenario prior to answering the question.
Your role is that of a consultant to the Lead Enterprise Architect in a multinational automotive manufacturer. The company has a corporate strategy that focuses on electrification of its portfolio and it has invested heavily in a new shared car
platform to use across all its brands. The company has four manufacturing facilities, one in North America two in Europe and one in Asia. A challenge that the company is facing is to scale up the number of vehicles coming off the production
line to meet customer demand, while maintaining quality. There are significant supply chain shortages for electronic components, which are impacting production in response to this the company has taken on new suppliers and has also taken
design and production of the battery pack in-house.
The company has a mature Enterprise Architecture practice. The TOGAF standard is used for developing the process and systems used to design, manufacture, and test the battery pack. The Chief Information Officer and the Chief Operating
Officer co-sponsor the Enterprise Architecture program.
As part of putting the new battery pack into production adjustments to the assembly processes need to be made. A pilot project has been completed at a single location. The Chief Engineer, sponsor of the activity and the Architecture Board
have approved the plan for implementation and migration at each plant.
Draft Architecture Contracts have been developed that detail the work needed to implement and deploy the new processes for each location. The company mixes internal teams with a few third-party contractors at the locations. The Chief
Engineer has expressed concern that the deployment will not be consistent and of acceptable quality.
Refer to the scenario.
The Lead Enterprise Architect has asked you to review the draft Architecture Contracts and recommend the best approach to address the Chief Engineer's concern.
Based on the TOGAF Standard, which of the following is the best answer?
A. For changes requested by an internal team, you recommend a memorandum of understanding between the Architecture Board and the implementation organization. For contracts issued to third-party contractors, you recommend that it is a fully enforceable legal contract. You recommend that the Architecture Board reviews all deviations from the Architecture Contract and considers whether to grant a dispensation to allow the implementation organization to customize the process to meet their local needs.
B. You recommend that the Architecture Contracts be used to manage the architecture governance processes across the locations. You recommend deployment of monitoring tools to assess the performance of each completed battery pack at each location and develop change requirements if necessary. If a deviation from the contract is detected the Architecture Board should allow the Architecture Contract to be modified meet the local needs. In such cases they should issue a new Request for Architecture Work to implement a modification to the Architecture Definition.
C. For changes undertaken by internal teams, you recommend a memorandum of understanding between the Architecture Board and the implementation organization. If a contract is issued to a contractor, you recommend that it is a fully enforceable legal contract. If a deviation from the Architecture Contract is found, you recommend that the Architecture Board grant a dispensation to allow the implementation organization to customize the process to meet their local needs.
D. You review the contracts ensuring that they address project objectives, effectiveness metrics, acceptance criteria, and risk management. Third-party contracts must be legally enforceable. You recommend a schedule of compliance reviews at key points in the implementation process. You recommend that the Architecture Board reviews all deviations from the Architecture Contract and considers whether to grant a dispensation to allow the process to be customized for local needs.