You want to prepare your ONTAP cluster and your ESXI cluster to connect NFS datastores over a 10-GbE network using Jumbo frames. In this scenario, which three configurations would accomplish this task? (Choose three.)
A. Enable jumbo frames with an MTU of 9000 for your ESXi hosts.
B. Enable jumbo frames with an MTU of 9216 for your switches.
C. Enable Jumbo frames with an MTU of 1500 for your ESXI hosts.
D. Enable Jumbo frames with an MTU of 1500 for your ONTAP cluster.
E. Enable Jumbo frames with an MTU of 9000 for your ONTAP cluster.
A node fails on an HA configuration. A successful failover occurs, but your clients that are using the SMB protocol complain that they are not able to access their data. In this scenario, what caused the problem?
A. The surviving node is not licensed for CIFS.
B. One of the cluster Interconnect ports on the surviving node failed.
C. The quota for the qtree has been reached.
D. The disk ownership did not transfer correctly.
An application owner at your organization requests a solution for zero RTO In the event of a failure In your primary data center, where you are using NetApp ONTAP 9.8 software with ISCSI LUNs. The owner wants to avoid reconfiguring the application.
Which NetApp solution would you propose to fulfill these requirements?
A. SyncMlrror
B. SnapMirror Business Continuity (SM-BC)
C. SVM Disaster Recovery (SVM DR)
D. SnapMirror Synchronous (SMS)