In a multiple programme environment, which role may be performed by a ‘corporate portfolio board’?
A. Sponsoring group
B. Programme board
C. Design authority
D. Programme office
Which role is MOST likely to have a focus on managing the costs of training operational teams during transition?
A. Business Change Manager
B. Programme Manager
C. Senior Responsible Owner
D. Programme Office
Which information about a project should be included in the Projects Dossier?
A. How the outputs will be implemented into the business
B. Contribution the project will make to the programme's benefits
C. Names of the project team members
D. Project brief for the project