Which of the following test types is a part of the V-Model?
A. Black-box testing
B. White-box testing
C. Experience-based testing
D. Component testing
Your task is to compile a test execution schedule for the current release of software. The system specification states the following logical dependencies: ?An admin user must create/amend/delete a standard user. ?A standard user is necessary to perform all other actions. The test plan requires that re-tests must be performed first, followed by the highest priority tests. To save time, the test plan states that tests should be scheduled to create test data for the subsequent tests in the schedule. The following test cases have been designed, with an indication of priority (1 being the highest priority) and whether the test has previously failed.
Which test execution schedule meets the test plan requirements and logical dependencies?
A. a, d, c, b, e
B. a, c, b, d, e
C. e, a, b, c, d
D. e, a, d, c, b
Which of the following is a factor that could negatively influence the success of the deployment of a tool within an organization?
A. Introducing the tool to all the test teams of the organization at the same time
B. Collecting usage information of the tool from the early projects.
C. Providing training and coaching for new users of the tool
D. Adapting and improving the processes to the usage of the tool