How does a project manager request a change to a resource plan in the requested state?
A. Use notes on resource plan.
B. Email resource user.
C. Request change on resource plan
D. Email resource manager
Which role can configure the parameters of the demand workbench that is provided with the base system?
A. All roles.
B. it_project_manager
C. it_pps_admin.
D. business_stakeholder.
Which roles can modify agile properties? (Choose two.)
A. it_pps_admin.
B. product_owner.
C. admin.
D. scrum_master.
What happens to the expense line after it is processed?
A. The actual cost is recorded at the portfolio level.
B. Nothing significant results.
C. The cost plan closes.
D. The actual amount incurred becomes part of the cost plan.
An it_project_manager can request resources by which of the following: (Choose two.)
A. Hours.
B. Person Days.
C. Month.
D. Day.
The information displayed on Project Workspace is setup in which table?
A. vtb_card
B. pm_project
C. pm_home_page_card
D. vtb_card_history
What role can configure the default columns in the project planning console? (Choose two.)
A. admin
B. it_project_manager
C. it_console_admin
D. it_pps_admin
A checklist item record provides a name and what other element?
A. Status field.
B. Complete field.
C. Percent complete field.
D. Short description field.
Expenses and costs for a particular demand should be estimated before screening. When preparing the financials of a demand, what determines the present value of future cash flows?
A. Financial Return.
B. Planned ROI.
C. Internal Rate of Return %.
D. Discount Rate %.
Which demand category would a demand manager select, if they need to create an enhancement?
A. Change
B. Strategic
C. Defect
D. Operational