Which of the following criteria on test progress would enable the business to determine a likely `go live' date?
(i) Number of tests planned versus number of tests executed (ii) Number of high priority defects outstanding
(iii) The test team's timesheets in order to show how much effort has been devoted to testing (iv) Number of tests passed and number failed (v) Number of defects found in each development area
(vi) The rate at which defects are being found
[K2] 1 credit
A. (ii), (iii), (iv)
B. (i), (iii), (v)
C. (i), (ii), (vi)
D. (iv), (v), (vi)
The use case will be used as a basis for the design of usability test scenario's. As a tester you are asked to review the ATM use case from the perspective of usability testing. As a tester you are asked to review the ATM use case provided below. The use case will be used as a basis for functionality testing to be performed later.
Which one of the comments, described hereafter, would be the MOST important one you would make? [K3] 2 credits
A. Acceptance criteria not defined
B. Business priority is missing
C. Post condition not defined
D. Alternative flows are missing
A SUMI test was performed at an early stage within the system test. Hereafter you find the results of the SUMI test.
Based on these results, what would you recommend as the most appropriate approach for usability testing? [K4] 3 credits
A. Since the SUMI scores are largely above market average no further action on usability is needed
B. Since the standard deviation of most SUMI scales is much too large, a new SUMI test must be performed
C. Since the scores are not really showing a high level of user-satisfaction additional usability testing based on use case is needed
D. Since the SUMI results do not provide details, an additional focused heuristic evaluation on the lower scales is recommended
You are applying pairwise testing and using orthogonal arrays. The following steps are all part of the process to be followed. i) Determine the number of choices for each variable ii) Map the test problem onto the orthogonal array iii) Construct the test cases iv) Identify the variables v) Locate an appropriate orthogonal array
What is the correct order of the above mentioned process steps? [K3] 2 credits
A. i, ii, iv, v, iii
B. iv, ii, v, iii, i
C. iv, i, iii, v, ii
D. iv, i, v, ii, iii
A company offering house insurance policies has several policy options. They depend on the following factors: -Building type: house, semi-detached, apartment building, cottage Material: wood, concrete, brick, mixed Location: city, suburb, countryside, wilderness It has been decided to use the pair wise test technique and apply 2-wise coverage. To design the test case an appropriate orthogonal array needs to be located. Which of the following orthogonal arrays is to be selected for testing the house insurance policies? [K3] 3 credits
A.
B.
C.
D.
A. Option A
B. Option B
C. Option C
D. Option D
How many invalid test cases can be identified from the "Route Calculation" state table provided? You may assume all actions are different and independent. [K3] 3 credits
A. 6
B. 8
C. 102
D. 12
A route calculation for a car navigation system has been developed using the following state table: How many test cases are needed to achieve 0-switch coverage? [K3] 2 credits
A. 3
B. 6
C. 7
D. 12
A new web site must operate correctly with different browsers (Internet Explorer, Google Chrome, Firefox,
Netscape, Mozilla), using different plug-ins (Realplayer, Mediaplayer), will be receiving pages from
different servers (IIS, Apache and WebLogic) and will be running on various server operation systems
(windows 2007, XP, Linux)
Which of the following test techniques will you use to test this new web site in its various environments?
[K4] 3 credits
A. pairwise testing
B. exploratory testing
C. use case testing
D. decision table testing
Working together with the test manager during test planning, which of the following activities is NOT expected to be performed by the test analyst?
[K2] 1 credit
A. Review the test estimates of the test manager
B. Review the test plan for non-functional testing
C. Organize adequate test resources
D. Being involved in risk management sessions
According to the ISTQB Advanced syllabus, which of the following would be the MOST effective method of communication between test team members who are distributed across several time zones? [K2] 1 credit
A. Accurate recording of defect information in the defect tracking system
B. Accepting frequent builds from the developers to keep all testers working on the same version at the same time
C. Skype meetings for personal interaction
D. Weekly, mandatory meeting with all personnel present