For the DEV project, Max has these requirements relating to time logging:
I need to be able to edit time logs.
I need to be able to delete time logs.
Which three project permissions does Max need in order to meet these requirements? (Choose three.)
A. Schedule Issues
B. Edit All Worklogs
C. Move Issues
D. Delete All Worklogs
E. Work On Issues
F. Edit All Comments
Which statement is correct about archiving a version in Jira?
A. Versions can be archived only in Jira Software projects, not Jira Business projects.
B. Archived versions cannot be selected in either the Fix Version/s dropdown, or the Affects Version/s field dropdown.
C. Archived versions can be selected only in the FixVersion/s field dropdown, not the Affects Version/s field dropdown.
D. Versions can be archived in Jira only if they do not contain any unresolved issues.
E. Archived versions will be grouped as Archived Versions in the FixVersion/s field dropdown.
Analyze the workflow scheme for the SSP project shown below:
Which change would require an update to the workflow scheme?
A. Task and Story need different screens when they are transitioned to Done.
B. Task and Story need a different screen when they are being created.
C. Epic and Bug need different screens when they are transitioned to Done.
D. Sub-task and Bug need a different set of required fields.
E. Task and Sub-task need a different set of required fields.