If in an experiment all possible variable pairs sum to zero the design is Orthogonal.
A. True
B. False
A Non-parametric Test should be used if just one distribution is not Normal out of the two or more gathered.
A. True
B. False
If a set of data is very similar in value yet far off the mark relative to the targeted value this data could be said to be:
A. Precise but not accurate
B. Accurate but not precise
C. Precise but skewed
D. Accurate but distributed
The distance between Quartile1 (Q1) and Quartile3 (Q3) is called as _____ and it helps to understand _____ of process variation.
A. Inter Quartile Range and Width
B. Quartile Range and Height
C. Quartile 2 and Width
D. Median and Width
The data set is having 100 values of effort variance in % for different project releases, indicate what type of distributions would be suited for understanding the process behavior.
A. Poison
B. Binomial
C. Normal
D. Exponential
Six sigma helps in:
A. reducing variation, removing waste and improving the process
B. improving the PandL
C. understanding customer specifications and billing the customer for the expenses
D. reviewing the process from time to time and increasing profitability
Cost of Poor quality (COPQ) does not include:
A. internal failure costs
B. external failure costs
C. appraisal costs
D. marketing costs
A key metric in Six Sigma is the DPMO which stands for __________________?
A. Delayed production metrics output
B. Defects by management oversight
C. Defects per million opportunities
D. Developed production management oversight
A Macro Process Map may map a process showing the entire activities of a department and can likely be broken into many Micro Process Maps showing numerous processes that comprise the activities of the department.
A. True
B. False
The following Business Case is constructed properly.
"During 2009 the commercial loan division experienced a 2.7% default rate versus a target of less than
.5%. This costs the bank in excess of $250,000 quarterly."
A. True
B. False