Which identifies the quality standards that are relevant to the project and how to satisfy them?
A. Quality Assurance
B. Quality Control
C. Quality Planning
D. Process Improvement
Identify two functions of the Project Management Plan [PMP].
A. defines the overall project management strategies and approaches
B. Is limited to project scope
C. Is the single most important work product produced by the Project Manager
D. Is limited to the project budget
E. Is done in project closure and is done only once
For our purposes, what is the most important work product produced by the project manager as prescribed by OUM Manage?
A. Project management Plan
B. Project Resource Plan
C. Project Estimate
D. Project Budget
E. Project Bid