When is "Store Period Performance" usually performed?
A. After each pay period
B. After the schedule is updated
C. After Job Services validation
D. After working hours to enhance performance
You are an implementation consultant working at a company where project schedules have been managed primarily with Microsoft Project, on individual desktops. The "projects" theoretically have been multiple-year projects. Your scope of work includes migrating project data from legacy project plans and setting up project planning standards. As you look into the current Microsoft Project plans, it becomes clear that the projects are not really multi-year projects. The plans have been managed by creating "new" projects within the old projects by skipping a few lines in what has become more of a program history.
What approach would you recommend to retain the legacy data (which is a mandated requirement in the new Primavera system), while moving forward with a "one project, one plan" process?
A. Import all MS Project plans directly into the P6 production database "as is."
B. Import MS Project plans but break out current in-flight work into separate projects.
C. Create new projects only for in flight work identified in MS Project plans.
D. Retire legacy project plans and start with new project planning standards.
Select the true statement regarding live or summarized data.
A. Live data is used for resource management.
B. Live data is used for portfolio management.
C. Summarized data is used for resource management.
D. Summarized data is used for project management.
By default, a role's limit is determined by_____________.
A. the manually entered value on the Limit tab in the Role Dictionary
B. the combined limit of all resources assigned to the role
C. the combined limit of all primary resources assigned to the role
D. the combined limit of all primary resources assigned to a project
What are two benefits of designating a resource as inactive?
A. All project history and costs are retained.
B. Budgets from past projects will remain intact.
C. The associated user's information will be automatically deleted.
D. Actual costs for past projects will be positively affected.
E. The resource is identified as unable to perform future work.
What is the process that must be followed by a system administrator to create a user?
A. Create an email account to confirm access after user setup.
B. Assign a global profile, project profile, and responsible manager.
C. Request approval from the user's manager before completing the profile.
D. Assign a role to the user before assigning security profiles.
In your project, cost and work effort is not subject to change. Which duration type should be used?
A. Fixed Units
B. Fixed Duration and Units/Time
C. Fixed Units/Time
D. Fixed Duration and Units
You are a project manager on a fixed-bid contract. This contract has actually been positioned as a "loss leader" within your company because it is your first contract with this customer. The hope is that you can prove yourself to the customer and win additional business at higher margins down the road. The margins for this contract are very slim.
What would be the best solution to set up in P6 to give you the visibility that you need to minimize the probable financial loss?
A. Set a Mandatory Finish constraint at each contractual milestone and track schedule performance against the constraint.
B. Set all activities in your project plan to Physical % Complete, and use Remaining Duration to track schedule performance.
C. Set all activities in your project plan to Units % Complete, and use Remaining units to track schedule performance
D. Set a Must finish By date at the project level, and track schedule performance using float in the project plan.
Select the statement that best describes "Manage Scenarios" functionality.
A. You can create a portfolio for your own use or for sharing.
B. You can view portfolio data in different forms.
C. You can capture a snapshot of project data.
D. You can select a portfolio to work with or execute commands.
Identify three types of activity codes.
A. Global
B. Activity
C. Project
D. EPS
E. WBS
F. Resource